ANALISIS HUBUNG SINGKAT PADA JARINGAN TEGANGAN MENENGAH 20 kV

PADA PENYULANG NIMBOKRANG 1 PT. PLN (PERSERO) ULP GENYEM

Authors

  • Yusup Pantu Universitas Cenderawasih
  • Ekawati M. Ohee Universitas Cenderawasih
  • Jakobus Kariongan Universitas Cenderawasih
  • Marthen Liga Universitas Cenderawasih
  • Aris Sampe Universitas Cenderawasih
  • Rosalina N. Revassy Universitas Cenderawasih

Keywords:

Short circuit fault current, distribution, nimbokrang 1

Abstract

PLN ULP Genyem is a unit that provides electricity services in Jayapura Regency, as a means to distribute electricity from substations to consumers of PT. PLN (Persero) ULP Genyem has several feeders, then to facilitate the author in this study, the author narrowed down the data taken from PT. PLN ULP Genyem Jayapura Regency. 20 kV PLN ULP Genyem distribution system on Nimobokrang Feeder 1. The purpose of this research project is to determine the magnitude of the 3-phase, 2-phase, and 1-phase short-circuit fault currents to the ground. The method used is sh ort circuit MVA. The data taken is in the form of secondary data taken from the ORYA hydropower plant and PT. PLN (Persero) ULP Genyem City. The initial step of data processing is to calculate the impedance, calculate the short circuit fault current. The calculation results obtained are the largest short-circuit fault current caused by a 3-phase short-circuit fault at 0% feeder length, which is 4787.38 A, and while the smallest short-circuit fault current is caused by a 1-phase short-circuit fault at 100% feeder length, which is 279.23 A. The farther the distance of the fault point, the smaller the short-circuit fault current that occurs and vice versa, the closer the distance of the fault point, the greater the short-circuit fault current that occurs.

References

Crystallography, X. D. (2016). No Title No Title No Title. 1–23.

Gaffar, A., Agussalim, A., & Arisandi, D. (2022). Analisis Gangguan Hubung Singkat Pada Jaringan Distribusi 20 Kv Di Gardu Induk Panakkukang. Jurnal Teknologi Elekterika, 1(2), 156. https://doi.org/10.31963/elekterika.v1i2.1221.

Kevin Gabriel Manopo, Hans Tumaliang, Sartje Silimang Jurusan Teknik Elektro, Universitas Sam Ratulangi Manado, Jl. Kampus Bahu-Manado, 95115, Indonesia

PLTA ORYA. (2024).

PT. PLN (Persero) ULP Genyem. (2024).

SPLN. (1985). Spln 64 : 1985 Petunjuk Pemilihan dan Penggunaan Pelebur pada Sistem Distribusi Tegangan Menengah. Departemen Pertambangan Dan Energi Perusahaan Umum Listrik Negara, No.172/DIR, 64. http://www.pln-litbang.co.id/perpustakaan

Vertex Elektro, Vol.12, No.02, Tahun 2020 (Agustus) p-ISSN. 1979-9772

e-ISSN. 2714-7487

Wahyudiyanto, D. B. (2009). Laporan kerja praktek pemeliharaan trafo distribusi dan program management pendataan kva trafo pt.pln (persero) apj bandung.

Downloads

Published

2024-03-03

How to Cite

Pantu, Y., Ohee, E. M., Kariongan, J., Liga, M., Sampe, A., & Revassy, R. N. (2024). ANALISIS HUBUNG SINGKAT PADA JARINGAN TEGANGAN MENENGAH 20 kV : PADA PENYULANG NIMBOKRANG 1 PT. PLN (PERSERO) ULP GENYEM. Jurnal Teletronic, 1(3), 17–21. Retrieved from http://teletronic.elektrouncen.com/index.php/teletronic/article/view/61

Issue

Section

Articles